Construction Loan Draws, Inspections, and Rates During the Build
Part 3 of our Arizona series follows the money during the build: how each draw gets requested, inspected, and funded, why your payment grows as the house climbs, what Arizona law does to protect your money, and how the loan finally becomes your mortgage.

Construction Loan Draws, Inspections, and Rates During the Build
AZ Construction to Permanent Loans · Part 3 of 3
Part 2 of this series ended at closing day, with your loan funded and the money sitting in a draw account instead of leaving in one wire. The money moves when the house does -- and this part follows it, draw by draw, from the first foundation pour to the day it becomes your mortgage.
How a draw actually happens
A draw is a payment from your construction loan, released as each phase of the build finishes. Nearly every construction lender runs the same four-beat rhythm: the builder requests a draw, the lender has the work inspected, the lender approves, and the money moves. The details belong to your lender -- federal loan rules talk about draws surprisingly little. Fannie Mae's only instruction about the money itself is that the lender "will be responsible for managing the disbursement of the loan proceeds to the builder, contractor, or other authorized suppliers" (Fannie Mae B5-3.1-02).
The common shape looks like this. Bankrate tells borrowers to "expect four to six inspections during the project" (Bankrate, January 27, 2026), and LendingTree's walkthrough uses five draws: foundation, framing with rough plumbing and electrical, exterior completion, interior finishes, and a final draw (LendingTree). The builder typically requests each draw as a phase wraps, and funding often takes a week or more. The "7 to 10 days" figure you'll see is one commercial estimate, so ask your lender for its real turnaround.
VA loans write one of those beats into the rulebook. The lender "must obtain written approval from the borrower before each draw payment is provided to the builder" (VA Lenders Handbook, Ch. 7), and the money sits in a draw account, paid out on the draw schedule once you approve each payment in writing. When a draw request lands, read it before you sign -- on a VA loan your signature is a required step.
One fee note: lenders charge inspection and draw-handling fees along the way, and those count toward your loan costs (CFPB, Regulation Z commentary). Every lender sets its own amounts. VA caps the flat charge its lenders may add for construction handling. It can reach 2% on top of VA's standard 1% when the lender supervises the build or advances more than half the loan, and 1% on top when it does neither (VA Lenders Handbook, Ch. 8).
The bill while you build
During the build, you pay interest only on money actually disbursed, "for the time it is outstanding," in the CFPB's wording (CFPB, Regulation Z commentary). Draw one funds the foundation, so month one's interest covers the foundation. Draw two adds the framing bill to the balance. By the final draw you're carrying interest on nearly the whole loan -- and your temporary payment has grown every month the house has grown.
What rate applies to that growing balance? Construction loan rates during the build are "usually" variable and tied to the prime rate (Rocket Mortgage, updated March 9, 2026; Bankrate, January 27, 2026), and they run above normal mortgage rates -- Bankrate puts the gap at about a percentage point over a 30-year rate, while LendingTree, citing Freddie Mac and NAHB data, measured construction borrowing 1.35 points more expensive in the third quarter of 2025 (LendingTree). Call it roughly a point to a point and a third -- both are commercial estimates of a moving target.
Lenders can build in a cushion called an interest reserve: a slice of the loan set aside at closing to pay the interest as it accrues, so the payment doesn't come out of your pocket each month (CFPB, Regulation Z commentary). The CFPB is upfront about the trade -- interest accrues on the reserve's payments too. VA loans can finance an interest reserve as part of project costs, and the veteran can pay interest beyond it when the reserve runs low (VA Lenders Handbook, Ch. 7). The reserve is borrowed money. It accrues interest like the rest of the loan, and a reserve sized for a twelve-month build runs dry if the build reaches sixteen months.
Some VA lenders offer a "ceiling-floor" arrangement where the veteran floats the rate during construction. The catch is that you must qualify for the mortgage at the maximum rate of that range (VA Lenders Handbook, Ch. 7). Your permanent rate, on a one-time close, was set back at the first closing -- Part 2 covered it.
When plans change: change orders and the contingency
Every build meets a moment where someone says "what if we..." That's a change order, and it has a paper trail on purpose. VA's rule is the model: change orders "should be reviewed in advance by the appraiser to ensure no loss in value," and changes made after the appraisal "cannot be mortgaged into the loan unless an updated appraisal is obtained" (VA Lenders Handbook, Ch. 7). A mid-build upgrade doesn't automatically ride on your financing -- it gets reviewed, and if it moves the home's value, the appraisal gets refreshed first.
This is also where the cushion for surprises from Part 2 earns its keep. Lenders call it a contingency, and the main fact about it hasn't changed: no federal rule sets its size, and the percentage figures online belong to renovation programs. Part 2's what-the-lender-finances section has the details.
Arizona's guardrails on your money
Arizona law gives homeowners building their own residence specific protection during the draw months. It's worth knowing about before you need it.
First, draw money is trust money in the law's eyes. Under A.R.S. § 33-1005, money paid by or for an owner-occupant -- someone building a home to live in -- to a contractor "shall be deemed for all purposes to be paid in trust" for the people who did the work and supplied the materials. The statute adds that those monies "shall neither be diverted nor used for any purpose other than" paying the claims the trust exists for. The trust follows the owner-occupant -- exactly who's reading this series -- and it preserves the beneficiaries' other remedies rather than naming a penalty of its own.
Second, the financing itself is protected. A.R.S. § 33-992 gives Arizona's mechanic's liens -- a subcontractor's or supplier's legal claim against a house for work they weren't paid for -- priority over anything that attaches to the home after work starts, with a carve-out for the construction lender. The lender's deed of trust -- the recorded security document behind the loan -- keeps its priority if it's "recorded within ten days after labor was commenced or the materials were commenced to be furnished." And the statute's "construction lender" includes "any assignee or successor in interest" (A.R.S. § 33-992.01), so the protection follows the loan through its conversion into your mortgage. The same article adds a homeowner-facing rule: no mechanic's lien against the dwelling of an owner-occupant "except by a person having executed in writing a contract directly with the owner-occupant" (A.R.S. § 33-1002) -- the subcontractor nobody hired can't lien your house.
Third, the paperwork has an official version. When a subcontractor or supplier gets paid, they sign a lien waiver -- a signed receipt saying this payment cleared and they won't file a lien over it. Arizona prescribes exactly four waiver-and-release forms -- conditional and unconditional, for progress and final payments -- and a waiver only does its job if it follows one of those forms. Anything informal is unenforceable unless the worker has already been paid in full (A.R.S. § 33-1008). A conditional release becomes effective when the check "has been paid by the bank," which is the statute's way of saying the release follows the money. The state's own pre-lien notice form tells homeowners exactly how to use this: require a conditional waiver before you make each payment, and an unconditional one after (A.R.S. § 33-992.01). Asking for the statutory form with every draw is a two-sentence email, and it's the single best habit in this section.
The last inspection and the certificate of occupancy
Toward the end, inspections stop being checkpoints and become the finish line. Cities and counties send their own inspector for the final walkthrough, and when it passes, they issue the certificate of occupancy -- the document that legally lets a homeowner move in. Scottsdale's own guidance puts it plainly: "Upon passing a Final Inspection, a Certificate of Occupancy (C of O) is issued, allowing ... a homeowner to move in" (City of Scottsdale, updated May 21, 2026).
On a VA loan there's one more guest at the final walkthrough: the original VA fee appraiser returns when the property is "100 percent complete" to certify that it meets VA's property requirements, was built to the plans and approved change orders, and held the value from the appraisal (VA Lenders Handbook, Ch. 7). VA accepts the local certificate of occupancy as evidence of satisfactory completion where the local authority performed those inspections.
The lender's file closes out with the appraisal side you met in Part 2. An appraisal update and completion report confirms the finished house matches the plans -- Fannie Mae requires it "in its entirety" at completion. If the report shows the value declined, a new appraisal and a re-check of the loan follow (Fannie Mae B5-3.1-02).
The conversion: how your loan becomes a mortgage
Then comes the moment the whole structure was built for. On a one-time close, "the construction loan will automatically convert to a permanent long-term mortgage loan upon completion of the construction" -- the terms were decided back at closing, and the loan simply changes hats (Fannie Mae B5-3.1-02). Freddie Mac's product works the same way: automatic conversion "with no change to the terms of the Note," or a one-time modification -- a formal, limited change to the loan's terms -- if the terms need to move (Freddie Mac 4602.2).
That modification is narrower than it sounds. Fannie Mae allows four narrow exceptions to the terms you set at the first closing: the interest rate, the loan amount (only to cover documented construction cost increases), the term, and switching from an adjustable to a fixed rate. Since May 2026, a rate or amount change within Fannie's standard tolerance rules doesn't even require re-running automated underwriting (Fannie Mae SEL-2026-05). What you don't do is start over: the credit and income refresh at conversion -- updated documents no older than 120 days, with the exceptions Part 2 covered -- is a paperwork update, not a second underwriting.
VA spells out the payment mechanics in unusual detail. Payments begin when construction is complete, and you repay the loan inside its remaining term: "If it takes six months to complete construction, the payment schedule for the Veteran obtaining a 30-year mortgage must provide for full repayment of the loan in 29 years and six months" (VA Lenders Handbook, Ch. 7). The build months don't extend the loan; they come off the front of the payoff schedule. And if rates have moved in your favor since closing, some lenders offer a float-down at conversion as a lender-specific option (NerdWallet, updated August 26, 2025).
Insurance, keys, and the warranty year
While the frame is open to the sky, the project needs its own coverage. Lenders commonly require builder's-risk coverage during construction -- a policy covering the half-built house against fire, theft, and vandalism, with the lender named on it (Rocket Mortgage, updated March 9, 2026). The policy ends "as soon as the house is ready to be occupied," when your regular homeowner's insurance takes over (Rocket Mortgage, updated July 27, 2026). On a VA one-time close, the handbook assigns hazard insurance during construction to the builder's side of the ledger (VA Lenders Handbook, Ch. 7). Who buys which policy is a contract question; write it into the builder's agreement.
After the keys: new builds commonly carry a builder's workmanship warranty of about a year (LendingTree). Walk the house during that window and put every defect in writing while the warranty is live. And if something goes wrong that the warranty doesn't cover, Arizona's ROC Recovery Fund exists for exactly that scenario -- Part 1's safety-net section covers the details.
When the schedule slips
Most builds run long somewhere, and the consequences arrive on three tracks. Interest keeps accruing on the outstanding balance -- that's arithmetic, not a penalty. Lenders may charge extension fees or adjust the rate when the loan outlives its planned term, and "may" is doing real work in that sentence: terms vary lender by lender (Rocket Mortgage; Bankrate). And the interest reserve from earlier can run dry, moving the interest payments back into your monthly budget.
The structural guardrails come from Part 2: Fannie Mae's single-close construction cap -- 12 months per period, 18 total -- is one of them, so a build wandering past a year needs a lender conversation. VA's handbook takes a different approach -- no extension rule, but built-in patience: the first principal payment can be postponed up to twelve months, with monthly delays of up to six more if needed (VA Lenders Handbook, Ch. 7). Either way, the moment a delay looks real, call your lender. Surprises are cheaper a month early.
Frequently asked questions
How does a construction loan draw schedule work?
The builder requests a draw as each phase finishes, the lender inspects the completed work, the lender approves, and the lender releases the funds -- typically four to six inspection stages over the project (Bankrate, January 27, 2026). Your lender sets the count and timing; no federal rule fixes it. On VA loans the lender must also get your written approval before each draw payment (VA Lenders Handbook, Ch. 7). Our Arizona construction loans guide shows a typical percentage-by-stage table -- treat it as a convention; your lender's schedule is the one that counts.
What are construction loan interest rates during the build?
Usually variable and tied to the prime rate (Rocket Mortgage, updated March 9, 2026). Construction loan rates run roughly a percentage point to a point and a third above 30-year mortgage rates: Bankrate pegs the gap at "about a percentage point" (January 27, 2026), and LendingTree, citing Freddie Mac and NAHB data, measured 1.35 points in late 2025 (LendingTree). You pay interest only on the funds disbursed so far.
Who pays the interest during construction?
You do -- from your own pocket each month, or from an interest reserve: a portion of the loan set aside at closing to pay interest as it accrues (CFPB, Regulation Z commentary). VA loans can finance an interest reserve as part of project costs (VA Lenders Handbook, Ch. 7). The reserve is borrowed money, and it accrues interest like the rest of the loan.
What is a certificate of occupancy and why does the lender care?
It's the document your city or county issues after the final inspection passes, and it's what makes the home legal to occupy (City of Scottsdale). Lenders tie the conversion to your permanent mortgage to completed, verified construction, so the certificate of occupancy and the lender's final inspection report are the two things they look for at the end (Fannie Mae B5-3.1-02).
What happens if my build takes longer than planned?
Interest keeps accruing on the outstanding balance, and lenders may charge extension fees or adjust terms -- the details depend on your lender (Rocket Mortgage). Fannie Mae caps single-close construction at 12 months per period and 18 months total (per Fannie Mae's guide; Part 2 has the detail), while VA allows the first principal payment to be postponed up to twelve months with up to six more monthly delays if needed (VA Lenders Handbook, Ch. 7). Call your lender as soon as a delay looks real -- extensions are easier to arrange before the deadline than after.
That's the whole journey -- budget, land, builder, loan, draws, and the morning the construction loan becomes a mortgage. Our Arizona construction loans guide is home base for all of it, and Part 1 is where the series starts. Or bring your plans to the person who'll walk you through it.
Call Michael George at AZWM at (480) 613-8040. Bring the draw schedule if you have one. We'll go through it line by line.
Michael George, NMLS #2280851 | Licensed in Arizona | Equal Housing Lender. Not a commitment to lend. All loans subject to credit approval.
Related Topics

Michael George
NMLS #2280851I'm an Arizona mortgage broker and I've helped buyers and homeowners across the state since 2001. I work with FHA, VA, Conventional, Jumbo, and USDA loans, plus refinancing — explaining every option in plain English so you can make the right call with confidence.
View more articles by this authorWhat Our Clients Say
Join thousands of happy homeowners who trusted us with their mortgage journey
Leon Bucci
FHA Loan"We are first time homebuyers, and we needed an FHA loan. We were pre-qualified for a great interest rate with only 3% down. We were so nervous, but our mortgage broker made us aware of all the pros and cons of several different mortgage programs. Call the Mortgage Genius-- 10/10!"
Michele Dutily
Refinance"Having a hard time finding the words to express how amazing my experience with Michael was. I will, however, refer anyone I know that is looking to purchase or refinance a home to Michael."
Judy Baeza
Multiple Loans"I had Michael George as my Mortgage Broker on two home loans & never worked with anyone so honest, helpful & competitively priced compared to other brokers I used."